What does the term fast tracking refer to in construction?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

Fast tracking in construction is a strategy used to shorten the overall duration of a project by overlapping phases of the project that are typically performed sequentially. This approach allows for the execution of design, procurement, and construction activities to occur simultaneously rather than waiting for one phase to be fully complete before starting the next.

For example, while the design of a building is being finalized, procurement processes for materials can begin, and some construction can commence on parts of the project for which design work has already been completed. This can significantly reduce the overall timeline of the project, allowing it to be completed more quickly than if each phase were carried out in isolation.

The ability to fast track a project depends on careful planning and effective communication among all parties involved, as overlapping activities can introduce complexities and potential risks. Utilizing fast tracking effectively can lead to earlier project completion and faster delivery of the final product, which can be advantageous in a competitive market.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy