What is the project delivery method called when the design and scope are partially undefined and the owner holds multiple contracts with various parties?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

The correct answer, which is Construction Management, refers to a project delivery method where the scope and design are not entirely defined at the outset. In this scenario, the owner engages with multiple contracts, often with various parties involved, such as subcontractors and suppliers, which allows for more flexibility in the project development process. This approach is particularly beneficial when projects are complex and require adjustments as the work progresses. The construction manager acts as a consultant to the owner, coordinating activities and ensuring that the project stays within budget and on schedule, addressing changes as they occur.

In contrast, design-build focuses on a single contract where one entity manages both design and construction, leading to more streamlined communication but less flexibility in terms of undefined scopes. General contracting typically implies a more traditional manner where a single contractor has a fixed contract for the entire project, reducing the owner’s engagement with multiple contracts. Traditional delivery methods often entail a sequential process where design is completed before construction begins, making it less adaptive when the initial scope is not clearly defined.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy