What items must be consulted to properly price a New Contract Change Order Proposal for a Road and Bridge Project?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

To properly price a New Contract Change Order Proposal for a Road and Bridge Project, consulting the Supplementary Conditions and the Prevailing Wage Rate Table is essential.

The Supplementary Conditions outline specific contractual requirements and modifications that are applicable to the project beyond the general conditions, affecting both the scope of work and potential costs. They help define what additional requirements or considerations may come into play due to the change order, ensuring that the contractor's pricing reflects any specific conditions dictated by the project.

The Prevailing Wage Rate Table is also crucial, as it details the minimum wage rates that must be paid to workers on public projects, which is especially relevant for road and bridge construction. Changes to the scope of work can involve additional labor costs that need to comply with prevailing wage laws, making it necessary to factor these rates into pricing accurately.

Understanding these two documents allows the contractor to prepare a well-informed and compliant change order proposal that reflects the true costs associated with the changes while adhering to legal wage requirements.