Which of the following is the proper Design Activity Sequence in a Design/Build logic network?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

In a Design/Build logic network, the proper Design Activity Sequence begins with the preparation of Schematic Diagrams. This initial step is crucial as it lays the foundational visual representation of the project and facilitates early discussions regarding design intent and functionality. Following the schematic development, the next step involves preparing Preliminary Plans, which further detail and refine the earlier diagrams, providing a clearer picture of the project's scope and design.

After the Preliminary Plans are established, the development of Contract Documents takes place. This step is essential to create the formal agreements, specifications, and legally binding documents required for the project execution. Finally, once the Contract Documents are complete, Issuing Bid Plans becomes the concluding step. This allows contractors and subcontractors to understand the project's requirements fully and submit their bids for the work.

This sequence logically flows from conceptual design to detailed planning and finally to the bidding process, ensuring that each stage informs the next in a coherent manner.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy