Which term refers to the process of following up on materials to ensure they arrive according to schedule?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

The term that refers to the process of following up on materials to ensure they arrive according to schedule is "expediting." This is a critical function in construction and project management because it involves actively monitoring the progress of ordered materials and supplies to confirm they meet their delivery deadlines. By effectively expediting, project managers can minimize delays caused by late or missing materials, ensuring that the workflow remains uninterrupted and that the project adheres to its timeline.

In contrast, procurement focuses on the process of acquiring goods and services, which encompasses negotiations and vendor selections, rather than the follow-up on timely delivery. Scheduling refers to the planning of various tasks and resources over time but does not specifically address the monitoring of material deliverables. Inspection is concerned with examining materials and work quality to ensure they meet specified standards, but it does not involve the proactive follow-up on the arrival of materials. Thus, expediting stands out as the essential term in this scenario, emphasizing the importance of coordinating and ensuring timely delivery in construction projects.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy