According to AIA documents, what must the Contractor request in writing after a claim rejection by the A/E?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

When a contractor's claim is rejected by the Architect/Engineer (A/E), the subsequent step involves the formal request for mediation in writing. This process is crucial because mediation serves as a structured method to resolve disputes outside of litigation. It allows both the contractor and the A/E to negotiate a resolution with the assistance of a neutral third party. The purpose of this request is to bring both parties together in an effort to reach an agreement, aiming to preserve professional relationships and minimize project delays.

The other options do not fit the scenario as effectively. For instance, a change directive involves changes to the work or contract but does not directly address the issue of resolving the claim. Similarly, a notice to proceed indicates the authorization to start work on a project but does not pertain to dispute resolution. A stop work notice halts all activities on the site and is more drastic, not suited for situations where mediation is sought to resolve a disagreement over a claim. Thus, requesting mediation is the appropriate course of action following a claim rejection by the A/E.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy