Which document would a contractor reference for installation procedures according to CSI?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

The correct answer is based on the structure and organization of the Construction Specifications Institute (CSI) guidelines, which are designed to standardize the process and terminology in construction documents. In CSI’s Project Manual, the document is divided into different parts, each addressing specific aspects of construction documentation.

Part 3 of CSI specifications specifically deals with the execution of the work, which includes installation procedures, quality assurance, and methods for carrying out the specifications. This part provides contractors with detailed instructions on how to implement the requirements outlined in the preceding sections. It serves as a crucial resource for ensuring that the installation meets both the design intent and code compliance.

In contrast, the other parts serve different purposes. Part 1 generally outlines administrative and procedural requirements, while Part 2 refers to product specifications, including materials and items to be used. Part 4, if applicable, usually pertains to other specific contract requirements or supplementary materials but is not typically standard across all CSI guides.

Understanding the purpose of each part allows contractors to locate the specific information needed for installation procedures effectively, reinforcing the importance of familiarizing oneself with the structure of CSI documentation.