Which of the following items is typically contained in the Certificate of Substantial Completion?

Prepare for the Associate Contractors License Exam. Study using flashcards and multiple choice questions, each question is equipped with hints and explanations. Get exam-ready today!

The Certificate of Substantial Completion serves as an important document in construction contracts, indicating that a project is sufficiently complete for occupancy or use, even if some minor work remains. One of the key components included in this certificate is a list of items to be completed, often referred to as a punch list.

This list identifies specific tasks or corrections that must still be addressed before the project can be considered fully complete. It provides a clear reference for both the contractor and the owner about what remains to be done, ensuring that everyone is on the same page regarding any outstanding obligations.

In contrast, the other options are not typically included in the Certificate of Substantial Completion. An estimate of final costs is generally prepared at a later stage, after all remaining work has been completed and costs tallied. Completion photographs may be taken for documentation purposes, but they do not form part of the formal certificate. Lastly, a schedule of future work might be relevant in other contexts but is not a standard component of the Certificate of Substantial Completion, which focuses solely on the current status of the completed work and any remaining items needed for full completion.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy